| General
Usage Guide: |
| |
| The
Pea Gravel should be placed into the prepared area as shown in the design plans. |
| Field
Estimating Quantities - Pipe Bedding Material
(In Place):
U.S.
| |
10 sq. yd. |
20 sq. yd. |
50 sq. yd. |
100 sq. yd. |
200 sq. yd. |
500 sq. yd. |
1000 sq. yd. |
| 6" Deep |
2t |
4t |
11t |
22t |
43t |
108t |
217t |
| 8" Deep |
3t |
6t |
14t |
29t |
58t |
144t |
289t |
| 10" Deep |
4t |
7t |
18t |
36t |
72t |
181t |
361t |
| 12" Deep |
5t |
9t |
22t |
43t |
87t |
217t |
433t |
| 18" Deep |
7t |
13t |
33t |
65t |
130t |
325t |
650t |
Metric
| |
10m2 |
20m2 |
50m2 |
100m2 |
200m2 |
500m2 |
1000m2 |
| 150mm |
2t |
5t |
12t |
23t |
46t |
116t |
231t |
| 200mm |
3t |
6t |
15t |
31t |
62t |
154t |
309t |
| 250mm |
4t |
8t |
19t |
39t |
77t |
193t |
386t |
| 300mm |
5t |
9t |
23t |
46t |
93t |
231t |
463t |
| 450mm |
7t |
14t |
35t |
69t |
139t |
347t |
694t |
|
| Supply
Locations: |
| |
| ·
Milford Sand & Gravel, New Hudson Plant |
| ·
Burroughs Materials, Holly Plant |
| ·
Burroughs Materials, Hartland Plant |
| ·
American Aggregate, Highland Plant |
| ·
American Aggregate, Oxford Plant |
| ·
American Aggregate, Ray Road Plant |
| ·
American Aggregate, Romeo Plant |
| ·
American Aggregate, Imlay City Plant |
|
|